The scope of the project involved L3 Design for Network Integration of 5MW Solar Farm to Essential Energy Network in Central NSW for one of our esteemed clients who have been developing numerous Solar Farms across the Globe.
ARTC requirements were also fulfilled as part of the Design as OHL from Grid to Solar Farm is crossing the Australia’s Inland Railway Line owned by ARTC.
Being an ASP in NSW, iEngineering’s team provides services to clients with L3 Design to Integrate their Solar Farms into the Grid.
Our consultants are also experienced of undertaking Network Impact, Power System & Earthing Studies for such projects.